8/23/08
6 Virtual Blackjack Tables and 300 Slots & have been delivered and installed with 100 more Slots on the way. The Grand Opening of the new gaming space is almost at hand!
6/18/08
The carpet is down and the final coat of paint is on its way.
5/21/08
The only thing you can say is "WOW"!
4/26/08
The lights are installed and tested. Let there be light!
4/8/08
The drywall is up so the primer can go on to prepare for the final color selection.
3/2/08
The work continues on and the room is starting to take shape .
2/2/08
The main level will host 500 VLT machines, food court, lounge complete with a stage and granite-topped bar and added restroom facilities.
1/26/08
The drywall is going up and the room is starting to take shape.
12/22/07
The mechanical, electrical, plumbing and HVAC work begin.
11/10/07
Over 300 cubic meters of concrete were used to pour the floors of the new gaming space!
10/13/07
The room is ready for concrete.
9/29/07
The steel starts going up. Over 700 tons of steel were used for this project.
7/20/07
Ground breaking. Removed all the stadium seating, dug and poured the foundations for the new gaming space.